Thursday 13 August 2015

August 12: Heating

We finally had the heating comissioned today.  Now we can start really enjoying our house!

It was a bit alarming to see our sustainable house using up to 60kWh a day to try and keep us vaguely warm!!

Thursday 6 August 2015

August 7: a new pipe

The plumber connected our gas meter this morning! Now we just need our heater commissioned!


Wednesday 5 August 2015

Tuesday 4 August 2015

July 30: some diggers

3 weeks late. Our gas line is installed



They managed to fill the house with gas and cut a Telstra line, nice work

Monday 3 August 2015

August 3: We're in!


Look! No dunny!










The girls checking out data cabling...


If only it was this neat inside and out now.  Six truckloads and numerous car loads had to go somewhere I guess.....