Friday 18 December 2015

December 18: more insulation

Today we had "Envirowall" insulation pumped into the remaining uninsulated walls.

Once the house cools off from this heat wave we'll be able to see if it makes any difference.









Sunday 29 November 2015

November 30: Security Door

Our security door was installed this morning. It hides our nice salvaged fromt door but is required for cross ventilation.  Now to get the fanlight operational...




Thursday 13 August 2015

August 12: Heating

We finally had the heating comissioned today.  Now we can start really enjoying our house!

It was a bit alarming to see our sustainable house using up to 60kWh a day to try and keep us vaguely warm!!

Thursday 6 August 2015

August 7: a new pipe

The plumber connected our gas meter this morning! Now we just need our heater commissioned!


Wednesday 5 August 2015

Tuesday 4 August 2015

July 30: some diggers

3 weeks late. Our gas line is installed



They managed to fill the house with gas and cut a Telstra line, nice work

Monday 3 August 2015

August 3: We're in!


Look! No dunny!










The girls checking out data cabling...


If only it was this neat inside and out now.  Six truckloads and numerous car loads had to go somewhere I guess.....



Wednesday 15 July 2015

July 16: Very very close

Today we had carpet laid in the upstairs rooms:

 


Some mroe upstairs shots:













...and now downstairs:



It's still strictly shoes off for the floorboards.














Saturday 4 July 2015

Jul;y 3: Front Door painted

We had to visit today to check the water meter.  it turns out somebody misread the meter and charged us for 102 kl instead of 2 kl.  So I got some door photos while I was there:



June 27: some digging

We had to do a bit of ground work to get the gas back in:





...and some more pics





...and the view from upstairs: