Saturday, 25 April 2015
Monday, 20 April 2015
April 20: insulation and Phase Change Material installed
The upstairs rooms, as well as being well insulated are having phase change materials (PCMs) installed to help moderate temperatures.
Sunday, 19 April 2015
April 19: I need a drink
Bottles are cleaned and filled ready for our thermal mass wall. We have around 110 bottles to install.
Thursday, 16 April 2015
April 17: Data cabling completed
To save a little cash and fopefully future proof ourselves a little we ran our own data cabling. Of course it was a good opportunity to take some more photos before the plaster goes up next week.
The scaffolding was picked up this morning
Our new bath!
More shots of the kitchen and pantry
Our stairwell and "Thermal Mass Wine Wall"
...with an initial selection...
Upstairs we see the start of installation of our insulation and phase change material
And finally my cabling shots so I remember where I put things....
The scaffolding was picked up this morning
Our new bath!
More shots of the kitchen and pantry
...with an initial selection...
Upstairs we see the start of installation of our insulation and phase change material
And finally my cabling shots so I remember where I put things....
Tuesday, 14 April 2015
Monday, 6 April 2015
April 7: Solar panels installed today
Our solar panels are being reinstalled today. I thought I should take some photos while up on the scaffolding
...and the view...
Wednesday, 1 April 2015
April 1: Half lockup stage
We visited site this morning, a few issues we need to make decisions on, but overall it's looking good
Views from the back
Upstairs rooms
What will be the stairs
The (mostly clad) Eastern outside wall