December 18: Slab Poured Today

Well the slab was poured today - just in time for Christmas
!









Posted by GirraweenGreen at 03:43 No comments:
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest

Tuesday, 16 December 2014

December 16: Slab preparation

Our slab is due to be poured tomorrow 






Posted by GirraweenGreen at 15:58 No comments:
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest

Monday, 15 December 2014

December 15: I can see some foundation excavations

Posted by GirraweenGreen at 02:41 No comments:
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Newer Posts Older Posts Home
Subscribe to: Posts (Atom)
  • Project Overview
  • Green Features

Blog Archive

  • ▼  2014 (7)
    • ►  October (1)
    • ►  November (3)
    • ▼  December (3)
      • December 15: I can see some foundation excavations
      • December 16: Slab preparation
      • December 18: Slab Poured Today
  • ►  2015 (30)
    • ►  January (1)
    • ►  February (4)
    • ►  March (2)
    • ►  April (7)
    • ►  May (2)
    • ►  June (3)
    • ►  July (4)
    • ►  August (5)
    • ►  November (1)
    • ►  December (1)
  • ►  2016 (5)
    • ►  January (1)
    • ►  June (1)
    • ►  July (1)
    • ►  August (1)
    • ►  October (1)
  • ►  2017 (2)
    • ►  February (1)
    • ►  September (1)

About Me

GirraweenGreen
View my complete profile
Scott Peucker. Simple theme. Powered by Blogger.